End-Area Earthworks Quantity Calculator
Cut-and-fill earthworks along a chainage using end-area cross-sections. Computes bulk volumes by SHW class, topsoil strip, and disposal.
Slug · end_area_earthworks · v1.0
Loading assembly schema…
End-Area Earthworks — a worked example, measured four ways
The same assembly at default dimensions, rendered as a Bill of Quantities under each measurement standard. Switch the standard to see how the bill changes. Change the inputs in the calculator to compute your own.
CESMM4 · 5 items · units m², m³
| Code | Description | Unit | Quantity |
|---|---|---|---|
| D.1.1 | General site clearance | m² | 2000 |
| E.2 | Excavation of topsoil for re-use or disposal, maximum depth not exceeding 0.25m | m³ | 300 |
| E.4.2.4 | General excavation, maximum depth 1-2m, commencing from existing ground level | m³ | 790 |
| E.5.3 | Disposal of excavated material off-site | m³ | 790 |
| E.6.1 | Filling, site-won topsoil, thickness 150mm, to landscaped areas | m³ | 300 |
Procurement take-off: the total quantity to order of each material, from the same compute. Supplier-neutral, so you buy anywhere.
- Disposal790 m³
- Excavation General790 m³
- Site Clearance2000 m²
- Topsoil Place300 m³
- Topsoil Strip300 m³
Illustrative example at default dimensions · engine ref 5b640c · not a tendered quantity